Digital planning as part of the Future Source major project
HOLINGER is coordinating the digital planning of the Lake Constance major water supply project to safeguard the drinking water of the future. A process plan defines the cooperation of the participating companies from the DACH region. A strategic decision was made to exchange data using an Open BIM approach. Models will be created using the open IFC standard and exchanged on a fortnightly basis. After quality checks, each model will be integrated into the coordination model. The coordination meetings will be held using model-based issue management in the cloud.
Our tasks
- Creation of a BIM approach for this major project
- Create and update the BIM process plan
- Manage the cloud platform and issues handling
- Act as the contact person for the BIM digital design of the project
- Oversee regular BIM digital design technical meeting
- Conduct model reviews and coordination every two weeks
- Quality management of the models